Port of Seattle – East Marginal Way Grade Separation
Description
The project involves environmental permitting including NEPA, SEPA and SMUP, design and construction of the grade separation project at the intersection between Spokane street and east marginal way in Seattle.
Scope of Work
Provide project scheduling services for the east marginal way (EMW) grade separation project involving scheduling with “pocket” schedules developed for the various players as requested.
Project Duration
2004
Value
Approx. CIP value of $25M